Rachel and Mike's Kitchen Punch List

by 9/2: Drywall finished (other contractor)

by 9/8: Remove, strip and re-hang last two windows with new sash chain

by 9/10: Finish stripping and shellac (2 coats) woodwork.

9/9 and9/10: Floors sanded and finished (other contractor)

9/11and 9/12: Install cabinets.  Cut holes in cabinet bottoms and install removable panels to for installation and maintenance of heaters

9/13: Schedule for measuring countertops (other contractor) - as soon as floor is done and cabinets installed

by 9/24: Heating installed (other contractor)

by 9/20: Finish electric (other contractor)

by 9/20: Have refrigerator and dishwasher delivered

by 9/20: Finish plumbing (and gas) (other contractor)

by 9/22: Prep and prime walls and ceilings

by 9/24: Paint ceilings

by 9/24: Install lighting fixtures

by 9/22???: Countertops installed (10 to 14 days after measuring)

by 9/24: Plumber install dishwasher. (other contractor)

by 9/24:  Install stove

Schedule final inspections for plumbing and electric.

Tile and grout back-splashes, and wall over stove (behind exhaust hood) --  after countertops are installed

Install range hood -- after tile is installed

Schedule final inspection

Install cloth/vinyl wall coverings

Fit drawers of old pantry cabinet with glides

Sand top of old pantry cabinet and varnish with tinted polyurethane to match shellac.

Repair entry door